| S.No. | Activity | Target | Achieved | Percentage |
| 1 | RCH Camp | 60 | 60 | 100% |
| 2 | Dai Training | 260 | 260 | 100% |
| 3 | IMNCI Training | 1026 | 609 | 59.35% |
| 4 | JSY | 15690 | 15794 | 100.66% |
| 5 | Institutional Delivery | 30117 | 18084 | 60.46% |
| 6 | IMMUNIZATION | 31708 | 28765 | 90.72% |
| 7 | TT to Pregnant Women | 37383 | 34060 | 91.11% |
| 8 | Sterilization | 7690 | 5844 | 75.99% |
| 9 | PCPNDT WorkShop | 1 | 1 | 100% |
| 10 | District Health Society Meeting | 12 | 12 | 100% |
| S.No. | Activity | Target | Achieved | Percentage |
| 1 | ASHA-SHAY. Selection | 881 | 756 | 85.81 % |
| 2 | Skill Birth Training | 48 | 48 | 100 % | 3 | Routine ImmunizationTraining | 520 | 264 | 50.76 % | 4 | BEmOC Training | 16 | 4 | 25 % | 5 | Blood Storage Training | 3 | 3 | 100 % |
| 6 | ASHA-SAHAY. MEETING | 396 | 359 | 90.65 % |
| S.No. | Activity | Target | Achieved | Percentage |
| 1 | Untied Fund Utilization SC | 4623317 | 3624071 | 78.39 % |
| 2 | Untied Fund Utilization PHC | 1250000 | 878651 | 70.29 % | 3 | Untied Fund Utilization CHC | 600000 | 425724 | 70.95 % |
| 4 | Village Health Sanition Committee | 1810000 | 1498039 | 82.76 % | 5 | Annual Maintenance to PHCs (Financial) | 1775000 | 942816 | 53.12 % |
| S.No. | Institution Name | Doctor Quarter | Paramedical/iV Class | Physical Progress |
| 1 | Lakheri | 4 | 5 | Completed |
| 2 | CHC Talera | 1 | 2 | Completed |
| 3 | Hindoli | 1 | 1 | Completed |
| 4 | CHC Kapren | 0 | 2 | Completed |
| 5 | CHC Nainwa | 4 | 5 | Completed |
| 6 | PHC Dabi | 0 | 2 | Completed |
| 7 | PHC Gothara | 0 | 2 | Work in Progress |
| S.No. | Name of Block | Name of CHC/PHC | Name of Sub Center | Status of Work |
| 1 | Talera | Talera | Jameetpura | Hand Over |
| 2 | Talera | Barundhan | Laxmipura | Hand Over |
| 3 | Talera | Suwansa | Bajad | Hand Over |
| 4 | Talera | Lambakho | Rajpura | Completed |
| 5 | Talera | Nim Ka Kheda | Gudha Nathawat | Roof Led |
| 6 | Talera | Dabi | Dhaneshwar | Completed |
| 7 | Kapren | Arnetha | Jaisthal | Foundation Level |
| 8 | Kapren | Dehikheda | Laban | Lintel Level |
| 9 | Kapren | K.Patan | Chitawa | Court Stay |
| 10 | Kapren | J.K.Barana | Gendoli | Completed |
| 11 | Kapren | Indergarh | Babai | Completed |
| 12 | Kapren | Sumandi | Chanda Khurd | Foundation Level |
| 13 | Hindoli | Hindoli | Petch Ki Bawari | Lintel Level |
| 14 | Hindoli | Hindoli | Devji Ka Thana | Work Order Given |
| 15 | Hindoli | Badanayagaon | Sathur | Work Order Given |
| 16 | Hindoli | Gothara | Dhowada | Ist Floor Proposed |
| 17 | Hindoli | Basoli | Khinya | Rood Led |
| 18 | Hindoli | Alod | Akoda | Completed |
| 19 | Hindoli | Dablana | Ranipura | Completed |
| 20 | Hindoli | Dablana | Ren | Lintel Level |
| 21 | Nainwa | Nainwa | Bambuli | Work Order Given |
| 22 | Nainwa | Dei | Gudhadevji | Handover |
| 23 | Nainwa | Dugari | Bhajneri | Completed |
| 24 | Nainwa | Jajawar | Sisola | Completed |
| 25 | Nainwa | Bansi | Gudha Sadavertiya | Hand Over |
| 26 | Nainwa | Bamangaon | Samidhi | Completed |
| 27 | Nainwa | Karwar | Jarkhoda | Pinth Level |
| 28 | Nainwa | Talwas | Pipalya | Completed |